Regular Published Hub Progress Gallery
Work started on the refurbishment of the hub on 13th March 2018. The refurbishment is being carried out by Keller Construction Ltd an award winning construction company based in Ashby De La Zouch.
- November 2016
Photos taken before and refurbishment work
- December 2016
After clearance of building
- March 9th 2018
Security fencing now in place ready for work to start next week
- March 16th 2018
Work starts in earnest. Stripping walls floors and ceilings.
- March 23rd 2018
Still stripping out the old building
- April 6th 2018
CarPark cleared ready for extensions. Kitchen Stripped, floors up
- April 9th 2018
Extension foundations started
- 13 April 2018
Foundations, flooring, stud walls and beams
- April 17th 2018
Window designs finalised
- April 27th 2018
The extensions are going up and work continues in the offices
- May 3rd 2018
Work continues with the extension and inside
- May 14th 2018
Second floor stairs and toilets
- May 22nd 2018
Extension roof and heating system
- June 7th 2018
The roof goes on
- June 12th 2018
- June 22 2018
The new roof does on
- June 26th 2018
Pastering electrics and IT cabling going in
- July 5th 2018
New roof, New front door, progress in function room, library and offices
- July 13th 2018 The Painting Starts
- Aug 1st 2018
Its starting to look almost finished in places
- Aug 21st 2018
Almost finished
- Aug 28th 2018